Window Replacement Project

Schedule Update as of 24-March-2017

Below is the current replacement schedule for 261 Botanica Private:
(You must be logged in to see the details)

Units 71/67/63/68 Week of April 3rd 2017
Units 72/64/73 Week of April 10th, 2017
Units 69/65/74/70 Week of April 17th, 2017
Units 66/61/62 Week of April 24th, 2017
Flashing and caulking Week of May 1st, 2017

There will be no work on Good Friday, 14 April 2017

You will receive a confirmation notice of installation at your door at least 48 hours in advance of installation.
Please note the following:

  • Blinds, curtains and valances around windows must be removed.
  • Sufficient clearance (four feet of space) around the windows is needed for installers to work. (It is understood that this is not possible in some cases so your best efforts to make room is appreciated.)
  • Make sure there is a clear path from unit entrance door to windows

Please note also that the schedule will be subject to change during the project.
If you have any questions regarding preparations for this project, please contact the service office or our manager.

Other dates will be posted as they are known.

CCC No. 382